Tec-Option
Tec Option Home Page
About Tec Option
Contact Us
Tec-Option Advantages
Tec-Flex Assembly System
Nut & Stud Welding Equipment
Multi Spot Welding Equipment
Robotic Welding  Systems
Equipment Descriptions
Welding Equipment Videos
Engineering & Support Services
FAQ About Welding Systems
Industry News
Case Studies
Press Releases
Circle of Life
Testimonials
Part Gallery
Road Show
Link Partners
Sign Up

CASE STUDIES - Customer Cost Savings

New Process without New Capital - An existing customer needed to perform a hot-upset weld for a new project. Due to the flexibility of Tec-Option's design, only a new tool module was designed for the part and put into their existing machine, which was designed and built five years earlier. While we're unable to predict the future, our flexible systems are designed with the unknown in mind. How many machines do you own that are capable of such a feat?



Contingency Planning of Actual Manufacturing Volumes- All the forecasting of automotive manufacturing volumes cannot predict the cost of a gallon of fuel, which ultimately dictates the vehicle market. For example, when the cost of fuel rose to over $4 a gallon last year, truck production went down. A customer with two plants producing truck parts was able to ship the tooling from Plant One to Plant Two, thereby consolidating the lower-volume truck part production to Plant 2 to maximize machine time. This freed up their machine in Plant One to make car parts, which were in higher demand. The flexibility of the Tec-Option system allowed for maximization of resources, following the change in the market without the need for new equipment.


Double Production / Less Space Demands of Existing Process- Requiring higher volumes than currently able to produce, a customer purchased a set of Tec-Option Flexible Systems to duplicate an existing process. Our design allowed for twice the current production rate, required half the number of operators and used a fraction of the floor space ' all with definite cost savings. As an extra bonus, the robots used for the current process were dedicated to a new process, saving the company the expense of new robots!

 


Maximize Capital Investment with Full Utilization of Machine Time- A customer had the necessity of making a large variety of parts (27) with volumes that did not require 100% available machine time. In addition, all the parts required a fastener to be attached. Due to the large variety of similar fasteners, the plant required automatic feeding equipment to reduce human error. The solution was to buy three machines and eight tool modules, set up so that the parts and volumes would maximize the machines' usage for the plant. Parts using common fastener types were assigned to the machine with that equipment to reduce the number of unique fastener feed systems. The savings were tremendous when compared to traditional machine building techniques- reducing 27 machines to 3- requiring a fraction of valuable floor space, sharing common fastener feeding equipment, utilizing unused machine time - all while saving capital and labor costs.


Floor Space / Delay of Capital Investment of over $1.4M- A new customer had the problem of a longer than usual production ramp-up time period that involved 26 parts. Because of the modular design, the tooling was easily separated from the capital equipment, allowing the real tooling costs to be identified as the end customer's responsibility. The flexibility allowed the initial purchase of only one machine, saving on capital spending. Each of the tools were built and developed on this single machine. As the volumes increased, the customer was able to realize return on investment and then afford to increase capital spending until the final count was achieved. This customer ended up with 26 tools and 22 machines but saved money over the long ramp-up period. In addition, floor space was utilized only when required to manufacture parts.


Three Value-Added-Process Parts in a Single Flexible Tooling Module- This particular solution allowed the customer to spot weld two parts together, pierce a hole, then weld a fastener over the hole in one tool module. All this was completed in three cycles and would yield a finished part every cycle during production. The operator loaded a fresh set of parts in the first station (left), where they were spot welded together. After the cycle was completed, the welded part was moved into the second station (center), and the first station was loaded again. The second station pierced a hole in the part, readying it for the next process. After the cycle was completed, the third station (right) was loaded with the pierced part, the second station was loaded from the first, and new parts were loaded into the first station. The third station would auto-feed a fastener and weld it over the pierced hole, then unload the part onto a conveyor. For every cycle, each station would apply its process to the part, completing one part per cycle. Not only did this reduce WIP and part handling, but the cycle was completed in less than 7 seconds and with a higher level of quality control than if performed in separate machines by separate processes. Automatic part tracking would enable/disable the appropriate stations for lead-in or run-out, reducing operator intervention.


Engineering Changes Easily Managed- A customer in Mexico had a PPAP due date only weeks away, yet required an engineering change to their project. Due to the modular design, only the tool module was required to ship to Tec-Option for the changes, saving time, shipping charges, customs inspections and the resources normally used to connect and disconnect the machine's utilities. Because of the complexity of the change, the design also eliminated the necessity of flying in support personnel to make changes onsite, eliminating all the associated travel expenses. While the tool was in transit, the additional purchase items were ordered and received. The changes were made, verified in a test machine at Tec-Option, and the tool was turned around and received by the customer in less than a week. This allowed for a successful, timely PPAP and satisfied the requirements for acceptance of the part on schedule.


Next Day Shipping (special situation)- A Tec-Option customer called needing to increase part production; they did not have any available machine time and were paying employees over $10,000 a week in overtime. They were desperate for more machine time and wanted to know how soon they could obtain another machine. Because of the flexible design of our modular system and the standards used in the building process, they purchased Tec-Option's test machine on our production floor one day, and it shipped the next day. In less than three days, the company was building parts to order at the new volumes. The only incompatibility of the machine shipped was that the paint color did not match their specifications! (This was not an issue.) Although next-day delivery is the exception to the rule, it was possible because of the flexible design and standards that are used in building our systems.


Manufacturing Volumes Not to Quoted Rates- Many customers have purchased one machine and multiple tooling modules for lower volume projects. When the volumes increased to a point where one machine was not enough, additional machines were purchased to handle the extra volume as cash flow improved.


Reduce Cost by Eliminating Auto-feed Fastener Equipment- Some customers have a need to affix fasteners but do not have the budget to purchase the auto-feeding equipment. By creating dual-station tooling with part auto-unload in one machine, there is more time available to hand-feed fasteners in one station while the other station is in process. The dual-station not only allows extra load time, it also is continuously processing parts in the opposite station. This effectively eliminates operator load time and the cost of auto-feed equipment, and realizes 100% machine time as well.

 

 

 


 
 
 
Nut & Stud Welding Equipment | Multi Spot Welding Equipment
Robotic Welding & Welding Automation Equipment | Engineering & Support
Site Map

Tec-Option, Inc
334 Sherman Street, Blissfield, MI 49228 Phone: 517.486.6055  Fax: 517.486.2352
Copyright © 2009